Remote planning shows an empty field, but the site survey finds temporary fencing that channels pedestrians directly beside the intended launch area. What should the pilot do with the original route?

Answer

Reassess the launch area and route using the pedestrian flow that actually exists. Move the operating area, add effective controls, or change the mission if the required separation cannot be maintained.

Explanation

Temporary site arrangements can create risks that are invisible on maps. The on site survey exists to test the plan against the current environment.